Received an HSE Improvement or Prohibition Notice? What to Do in the First 21 Days

Download the notice response tracker (Word) (DOCX · 13 KB) · the tracker to print (PDF) (PDF · 34 KB)

What should you do on the day the notice arrives?

Make it safe first. A prohibition notice stops an activity. The Act says the stop takes effect at the end of the period in the notice or, "if the notice so declares, immediately". If it is immediate, the activity stops now, on every shift, until the matters in the notice are put right. HSE's leaflet puts it simply: "A prohibition notice orders you to stop doing something until you have made it safe to continue."

Diary the dates. Find the date the notice was sent, and work out the end of the 21-day appeal window from it. Then find the compliance date in the notice. Put both where they cannot be missed, with a named owner.

Tell the people who need to know. That usually means:

Keep the paperwork together. The notice, any letter that came with it, notes of what the inspector said and photos of the area as it was on the day. You will need them for the tracker, for an appeal decision and for any later questions.

How do you read the notice and its schedule?

The Act sets out what a notice must contain, which tells you where to look.

So read the schedule line by line, and copy each requirement into the tracker as its own row, in the inspector's words. Where the notice gives a choice of remedies, record which one you chose and why. Where a requirement is unclear, ask the inspector what would satisfy it, and note the answer with the date.

Can you get more time?

Sometimes. The Act allows it: for an improvement notice, or a prohibition notice that does not take immediate effect, "the period so specified may be extended or further extended by an inspector at any time when an appeal against the notice is not pending" (s23(5)(b)).

That is a power the inspector may use, not a right. HSE does not publish a fixed process for asking, so these are practical points rather than HSE's position:

Should you appeal?

Only you can decide, ideally with advice. The deadline is fixed: an appeal must be received by the employment tribunal "before the end of the period of 21 days beginning with the date on which the notice which is the subject of the appeal is sent to the appellant", unless the tribunal allows longer because that was not reasonably practicable (ET Regulations 2013, reg 14A).

Before going formal, HSE's leaflet suggests talking first: "Please contact your inspector or their manager before you start any formal dispute against one of our decisions. They may be able to look at the decision again."

What an appeal does to each notice (an improvement notice is suspended; a prohibition notice stays in force unless the tribunal directs otherwise) is covered in our overview of notices and appeals. Whatever you decide, keep the site safe while you decide.

How do you put the requirements right?

Treat each requirement as a small project with an owner, an action and an end date. Some practical points that hold up well later:

How do you show the inspector it's done?

The notice requires you to put things right. It is good practice to tell the inspector when you have, but HSE does not publish a set procedure for this, so ask the inspector how they would like to hear. A short letter or email works well: each requirement in the notice's words, what you did, the date, and the evidence attached or available. Keep a copy with the notice.

Two things to keep in mind. HSE's fee for intervention can include time "talking to you after the visit" and "the time spent helping you put things right", so clear, complete evidence also saves back-and-forth. And the inspector may visit again to check.

What does the first 21 days look like?

When What to do
Day the notice arrives Make it safe (stop the activity if the notice says so). Diary the appeal deadline and the compliance date, each with an owner. Tell the responsible director, affected managers and safety representatives.
Days 1–3 Copy every requirement from the schedule into the tracker. Ask the inspector about anything unclear. Brief every shift in the affected area.
By day 7 Agree an action, owner and date for each requirement. Order parts or book contractors. If the compliance date looks tight, ask for more time in writing.
By day 14 Decide whether to appeal, with advice if you are considering it. Talk to the inspector first.
Before day 21 If appealing, make sure the tribunal receives it in time. If not, keep going with the fixes.
By the compliance date Every requirement done and evidenced. Tell the inspector, in writing.
After Check on normal shifts, including nights, that the fix still holds.

What does this look like in practice?

A distribution centre receives an improvement notice after an inspection. The schedule has two requirements: separate pedestrians from lift trucks at the goods-in doors, and review the workplace transport risk assessment.

How do you know the fix is holding?

A notice is put right by a date. The harder test is whether the change still holds months later, on a busy night shift with agency staff. Plan checks at different times and shifts, and record what you saw, not only that you went. Our guide to proving your traffic management controls work covers what good evidence looks like. Some sites use fixed cameras for this, such as RoboK SiteLens, which records near misses and people in vehicle routes in the areas the cameras cover, so a team can see whether a change has held.

Common questions

What should I do if I get an improvement notice from HSE?

Make the area safe, diary the appeal deadline (21 days from the date the notice was sent) and the compliance date, and tell the people responsible. List each requirement in the schedule with an owner, an action and a date, keep evidence as you complete them, and tell the inspector in writing when it is done. If you need more time, ask the inspector early.

Can an HSE improvement notice deadline be extended?

Yes, an inspector can extend the period, under section 23(5) of the Health and Safety at Work etc Act 1974, but only while no appeal against the notice is pending. It is the inspector's decision. Ask in writing, before the deadline, with your reason, a date you can meet and how you are controlling the risk meanwhile.

How long do I have to comply with an improvement notice?

The period is set in the notice. By law it cannot end before the 21-day appeal period does, and HSE's leaflet says it will give "at least 21 days to make any changes".

What happens if I don't comply with an HSE notice?

It is a criminal offence under section 33 of the Act, and HSE's enforcement policy lists failure to comply with a notice among the circumstances where it would normally prosecute. In the Crown Court the maximum is two years' imprisonment, a fine, or both.

Do I have to tell HSE when I've complied with a notice?

HSE does not publish a fixed procedure, but it is good practice. Ask the inspector how they want to hear, then send a short written summary: each requirement, what you did, the date and the evidence.

Should I appeal an improvement or prohibition notice?

That depends on your case, and you should take advice. An appeal goes to an employment tribunal, which must receive it within 21 days of the date the notice was sent. HSE suggests contacting the inspector or their manager first, as they may be able to look at the decision again.

References

A notice is put right by a date. Whether the fix holds on the night shift three months later is the harder question. What would your records show? Safety Mapping: a free two-week trial on one camera.

Last checked November 2026