A site that has run for years has habits built around its layout. People know which way the forklifts
come from, where to cross, and where a driver can't see them. A change breaks some of that knowledge
without anyone noticing.
Three things tend to go wrong:
The routes in people's heads stop matching the site. People keep walking the old way, especially
where it's shorter. Our essay on desire lines
explains why.
Temporary arrangements during works. A route shared for "a few weeks" while machinery goes in can
carry more risk than either the old layout or the new one.
The plan on the wall goes out of date. The traffic management plan and site map show the site as
it was.
What does the law ask when you change a layout?
Review the risk assessment. The Management Regulations require a review where "there has been a
significant change in the matters to which it relates" (regulation 3(3)(b)). A change to vehicle
routes, crossings or visibility is an obvious example. Our guide to reviewing a risk
assessment covers how.
Consult the people affected. HSE's guide to managing health and safety (HSG65) puts it plainly:
"By law, you must consult your workforce about any change that may substantially affect their health
and safety." The duty in the Consultation with Employees Regulations 1996 covers "the introduction of
any measure at the workplace which may substantially affect the health and safety of those
employees;" (regulation 3(a)). Where there are union safety representatives, the parallel duty is in
the Safety Representatives and Safety Committees Regulations 1977.
Keep people and vehicles apart, during the works too. The Workplace Regulations say: "Every
workplace shall be organised in such a way that pedestrians and vehicles can circulate in a safe
manner." (regulation 17(1)) That applies on the day the barriers come down as much as when the new
layout is finished.
Before the change
HSE's guide to workplace transport safety (HSG136) says: "Think about new designs/layouts before they
are put in place. Also think about the effect of any changes in how things are done, eg different types
of vehicle, or having to use different or new routes." (paragraph 16)
Before work starts, answer these on the site plan:
What is changing, when, and is it temporary or permanent?
Which routes, crossings, turning areas and sight lines does it affect?
Will there be new types of vehicle, or more vehicle movements?
Who is affected? Think beyond your own staff: agency workers, visiting drivers, contractors and their
vehicles, and visitors.
Who have you consulted, and what did they say? HSG65's examples of changes to consult on include new
or different procedures, equipment, premises and ways of working such as shift patterns.
During the works: the transition is its own risk
HSE's guidance on organisational change was written mainly for major hazard sites and changes to
staffing and roles, but its principles carry over to a yard. It separates where you're going from how
you get there, and both need assessing. It also advises: "Avoid too many simultaneous changes which may
result in inadequate attention to some or all."
During the works:
Mark temporary routes and crossings as clearly as permanent ones, with barriers where vehicles and
people would otherwise meet.
Phase the work if you can, so only one area changes at a time.
Brief people before each phase, not after. HSG136: "If there are changes in the workplace which mean
that employees are exposed to different risks, make sure everyone receives suitable safety training
before they are exposed to those risks." (paragraph 253)
Give extra supervision to people working in a changed area, as HSE's organisational change guidance
suggests for new or changed roles.
Keep consulting: HSE's advice is to "Consult with staff (including contractors) before, during and
after the change".
After the change
Update the paperwork. The traffic management plan, site map, risk assessment and induction
material. Our traffic management plan template has a
review section.
Brief everyone before the new layout goes live, including nights and weekends. Our toolbox
talks are a quick way to do it.
Watch the first weeks. HSG136 asks you to monitor vehicle and pedestrian movements over a
reasonable period to get a clear picture (paragraph 15). After a change, look for people using the
old route and drivers taking new shortcuts.
Treat near misses as the early signal. HSG136: "It is important to have strong lines of
communication to ensure any changes can be quickly put into practice." (paragraph 22) A simple way to
report problems shows early whether the new layout works.
A worked example (invented)
This example is invented to show the method. It is not a real site.
A distribution centre moves two runs of racking to make room for a new sorter. The layout change check
shows that the forklift route to the new marshalling lane now crosses the walkway agency staff use to
reach the canteen.
Question
Finding
What changes, and for how long?
Two racking runs move permanently; a temporary route runs for three weeks during the sorter install.
Which routes and crossings?
The forklift route now crosses the canteen walkway at an aisle end with poor visibility.
Who is affected?
Agency pickers on all shifts, the install contractor's team.
Controls during the works
Temporary barrier, a marked crossing, a briefing at every shift start for the first week.
After the change
Traffic management plan and site map updated; review set for two weeks after go-live.
What the review found
People cutting the corner at the end of the barrier. The barrier was extended.
Real cases
October 2026, Barnsley: during the installation of new automated machinery, a company changed
its workplace transport routes so that ride-on pallet trucks and forklifts shared routes in a busy
stock loading area, with limited visibility and more vehicle movements. A 20-year-old worker on a
ride-on pallet truck was injured in a collision with a forklift. HSE found the route changes had not
been properly risk assessed before they were implemented. Fined £80,000. In HSE's press release, the
inspector stresses assessing changes "even where those changes may be temporary". (HSE press
release)
May 2026, South East London: at a waste site, the pedestrian entrance was padlocked so people
used the vehicle route. HSE's press release reports that the site's traffic plan was out of date
because the site's configuration had changed since it was produced, so it missed key pedestrian
movements. Fined £167,000. (HSE press
release)
Fill it in before any change to routes, racking, buildings or doors. It covers what's changing and
when, the routes and crossings affected (with space to sketch), new vehicles or more movements, who's
affected, controls during the works, who was consulted, the risk assessment and traffic management plan
update, the briefing, and the first-weeks review.
Do I need to redo my risk assessment if the site layout changes?
You need to review it if the change is significant. The Management Regulations require a review where
"there has been a significant change in the matters to which it relates". A change that alters vehicle
routes, crossings or visibility is the kind of change to review for. Review the rows the change touches, and
record what you changed.
Do I have to consult staff about layout changes?
Yes, where the change may substantially affect their health and safety. HSG65 says: "By law, you must
consult your workforce about any change that may substantially affect their health and safety." Consult
before the change, during the works and after.
What is management of change in health and safety?
A planned way of making sure a change, to a layout, equipment, process or organisation, doesn't bring
in new risks unnoticed. It means assessing the change and the period while it happens, consulting the
people affected, communicating it, training before people meet the new risks, and checking afterwards.
HSG65 asks you to "Ensure that communication is included in change management procedures."
How often should a traffic management plan be updated?
HSE's guidance doesn't set a fixed interval. Update it whenever the site changes significantly, after
an incident or near miss that shows a gap, and when you review your risk assessment. A plan that no
longer matches the site can mislead the people who rely on it.
How do you manage temporary traffic routes during works on an operating site?
Assess the works period as its own risk, not only the finished layout. Mark temporary routes and
crossings clearly, use barriers where vehicles and people would otherwise meet, brief people before each
phase, add supervision, and agree with the contractor who manages their vehicles on your site.
Sources
The Management of Health and Safety at Work Regulations 1999, regulations 3 and 7.
The Health and Safety (Consultation with Employees) Regulations 1996, regulation 3.
The Safety Representatives and Safety Committees Regulations 1977.
The Workplace (Health, Safety and Welfare) Regulations 1992, regulation 17.
Health and Safety Executive (2014). A guide to workplace transport safety (HSG136), 3rd edition, paragraphs 15, 16, 22 and 253.
Health and Safety Executive (2013). Managing for health and safety (HSG65), 3rd edition.
Health and Safety Executive. Organisational change (human factors). hse.gov.uk/humanfactors/topics/orgchange.htm.
HSE press releases, 12 May 2026 and 23 October 2026 (linked above).
Which route on your site changed most recently, and are people using the new one? Safety Mapping: a free two-week trial on one camera.