Part of our workplace transport guide: step 5 of 7
Download the shutdown and restart plan (Word) (DOCX · 38 KB) · Download the shutdown and restart plan (PDF) (PDF · 25 KB)
Equipment doesn't stay as it was left. HSE's lifting equipment code (L113) says "environmental influences may cause equipment to deteriorate when it is not in use."
The rules on inspection allow for this. For work equipment exposed to conditions that cause it to deteriorate in ways that could become dangerous, PUWER requires inspection "each time that exceptional circumstances which are liable to jeopardise the safety of the work equipment have occurred". HSE's PUWER code (L22) gives examples: "Exceptional circumstances which may result in the need for inspection include:" and one of them is "substantial change in the nature of use, for example from an extended period of inactivity."
For lifting equipment, including lift trucks, L113 says: "A thorough examination is also required following any significant change which may affect the safe operation of the lifting equipment." The examples it lists end with "long periods out of use".
What that means for your site: a Christmas break may need an inspection or examination for some equipment. Whether it does depends on the equipment, how long it stood and where. Ask your competent person or examination scheme before you close, not on the first morning back.
Keys and start-up. HSG136: "Make sure keys are never left in an unattended vehicle and are securely stored when vehicles are parked in workplaces overnight, at weekends or for long periods." L22 adds: "Self-propelled work equipment should be prevented from unauthorised startup."
Use the break for maintenance, and plan it. HSE's advice on maintenance is to "try to use downtime for maintenance. You can avoid the difficulties in co-ordinating maintenance and production work if maintenance work is performed before start-up or during shutdown periods". It also names the risks: a hazard where "machinery starts up unexpectedly", and "This can be a particular problem if maintenance is during normal production work or where there are contractors who are unfamiliar with the site." Brief contractors on your yard rules and vehicle routes, even with the site quiet: see contractors and vehicles on your site.
Decide who signs each machine back in. For every truck, loader and item of lifting equipment: is it due an inspection or examination, is any repair booked over the break, and who confirms it is safe before it is used again?
Batteries. Agree what stays on charge over the break, and check the charging area on the first day back. HSE's battery guidance notes: "Hydrogen and oxygen are produced more quickly as the battery gets close to being fully charged."
Layout changes. If racking, routes or loading bays will change over the break, write them down now so the first shift is briefed. Our guide to changing a site layout has a one-page check.
Welfare water. For showers and taps that will stand unused, HSE's legionella guidance says: "For infrequently used outlets, instigate a programme of regular flushing (weekly)."
Walk the yard before the first vehicle moves. Check lighting, routes, barriers and signs, and the surface. If there has been snow or ice, HSG76's examples of what to do include "gritting, snow clearing and closure of some routes, particularly outside walkways, yards or gantries." For lighting in the dark early weeks, see our insight on dark yards after the clocks change.
Every truck checked before it moves. L117: "At the beginning of each shift, the operator should check the lift truck in accordance with the vehicle handbook and document the results." That includes "a functional test on the parking brake, service brakes and steering gear", and "Where visibility aids are fitted, include their condition and correct setting as part of the daily checks." HSG136: "Employers should give drivers a list of daily checks to be signed off before vehicles are driven."
After a break, give the checks the time they need, and don't let a backlog push the first truck out early. L113 calls the operator "the first line of defence in identifying any faults or damage", and the aim of such checks "is to pick up faults due to day-to-day wear and tear and malfunction of safety-related equipment."
Defects reported, not driven round. L117: operators "should report to the supervisor any defects which might affect its safe operation to ensure they are put right." HSG136 asks for "a simple system for reporting any problems".
Anything repaired over the break confirmed safe first. HSE's inspection guidance: "Work equipment that requires inspection should not be used, unless you know the inspection has taken place."
The full daily checks are in our guides to forklift accidents and L117 in plain English.
Treat the first shift back as a handover: what changed, what was repaired, what is still out of use, where contractors worked. Our guide to shift handover on sites with vehicles has a format.
HSE's checklist question fits January: "Are there changes in workers – new people who haven’t been on site before and who need information?" If the site changed over the break, the Management Regulations require a review of the risk assessment where "there has been a significant change in the matters to which it relates".
A backlog of deliveries can make the first days back busy. Our peak season traffic check works for that week too.
This example is invented to show the method. It is not a real site.
A manufacturer closes from 23 December to 4 January. In early December, the site manager fills in a two-column plan.
Before we close: keys collected and locked away by the shift supervisor on the 23rd; two forklifts booked for servicing on 28 December, with the contractor briefed on routes; the engineer asked whether the reach truck needs an examination after the break; one battery left on charge, the rest disconnected; a new one-way route by the goods-in door planned for the break.
First shift back: the supervisor walks the yard at 06:00 before any vehicle moves; each truck checked and signed before use; the two serviced forklifts confirmed safe by the engineer's report; a 10-minute briefing on the one-way route.
In a forklift case from Castleford that HSE announced in December 2025, HSE said: "HSE found the forklift had not had a full inspection to ensure it was safe to operate after repairs." The point for a restart: anything repaired over the break should be confirmed safe before it is used. The full case is on our forklift accidents page.
Download the plan (Word) · PDF. Free, no sign-up.
One page, two columns: before we close, and the first shift back. Fill it in early in December and pin it up for the first shift.
Walk the yard before any vehicle moves (lighting, routes, barriers, signs, surfaces), check every truck against its handbook and sign it off before use, confirm anything repaired over the break is safe, and brief the first shift on what changed.
They may. HSE's lifting equipment code says a thorough examination is required following any significant change which may affect safe operation, and lists long periods out of use among the examples. Whether a Christmas break counts for a particular truck is for your competent person and examination scheme to decide: ask before you close.
Yes. HSE says keys should never be left in an unattended vehicle and should be securely stored when vehicles are parked for long periods, and that self-propelled equipment should be prevented from unauthorised start-up.
HSE suggests using downtime for maintenance, which avoids co-ordinating it with production. Plan for the risks HSE names: machinery starting up unexpectedly, and contractors who are unfamiliar with the site.
As a handover: what changed over the break, what was repaired or is still out of use, where contractors worked, and who is new. If the site changed significantly, review the risk assessment.
When the yard comes back to life after the break, what will the first hour look like? Safety Mapping: a free two-week trial on one camera.
Last reviewed November 2026